The recent rains have obviously slowed down some progress of the project. The Contractor is trying to take appropriate steps to try and get back on track. They have recently subcontracted the installation of the sod on all finished work. We have recently completed the work on hole #4, #3, and #13. We have a little more work to do on #4 and #13 in the way of seeding of turf. The first cut (step cut) or rough on #4 will soon be moved to the new edges of the fairways. The areas of rough where the turf is stripped will then be seeded. With any luck we will have good weather in October and be able to make up some ground before we have to shut the project down for the Winter.